Time Line for Bouchier Creek

[To Item Page] 6. Lowering into ditch
Installation Timeline: 0 hours 22 minutes Lining up pipe ends.
[To Item Page] 7. Setting and leveling
Installation Timeline: 0 hours 27 minutes Setting base - assembling coupling in place.
[To Item Page] 8. Clamping coupling in place
Installation Timeline: 0 hours 37 minutes After coupling installed sling is removed.
[To Item Page] 9. Backfill and hand tamp complete
Installation Timeline: 0 hours 52 minutes
[To Item Page] 10. Rip Rap and sod to complete.
Total install time: 1 hour 07 minutes Including backfill and compaction Photo shows: Sod replacement took place following the above timeline.