Time Line for Bouchier Creek

[To Item Page] 1. Bouchier Crk. Culvert replacement
Fixed Spigot Headwall has an FRP or Enviro Connect spigot permanently fixed to the headwall. Fixed spigot is only standard in the 1.5 and 2 Series Headwalls. All others Xport.
[To Item Page] 2. Installing Culvert Crossing
CSP pipe replaced existing decayed wooden culvert. 2 x 5 Series headwalls c/w 1200mm CSP used to protect fish habitat for inlet and outlet ends.
[To Item Page] 3. Delivery to job site and base prep
Time Line 0 hours 7 minutes Culvert pipe already installed the prior day.
[To Item Page] 4. Slinging and unloading
Installation Time Line 0 hours 17 minutes Note simple sling - this would not be possible with a pre-cast concrete equivalent weighing approx. 12,000 lbs.
[To Item Page] 5. Lifting headwall into place.
Installation Timeline 0 hours 22 minutes Note: Lower half of pipe coupling was placed prior to dropping headwall into place.